题目内容

Management Reserve can only be expended with the()authority

A. Enterprise
B. Project manager
Clients
Designer

查看答案
更多问题

Methods of feasibility analysis include()

A. Simplified Method – ignore timing of benefits and costs
B. Payback Period
C. Entropy Methods
Discounted Cash Flow

The cost management plan can establish the following:()

A. Units of measure
B. Control thresholds
C. Rules of performance measurement
D. Reporting formats

Which is the independent variables that tracked by Earned Value Analysis()

A. Net Present Value
B. Value of work planned
C. Discounted Cash Flow
D. Annual cash flow

The cost types include:()

A. Direct cost
B. Indirect cost
C. Direct overheads
D. General and administrative cost