You are assessing the cost for a software development project. You discovered that, except for buying CAD application software, you need to hire some staff to plot on it. And more drawings you have, the unit cost will be less. This is because of:你在评估一个软件项目的成本。你发现,除了购买CAD软件费用外,只要雇用人,进行画图,就可以了。这样,你画图越多,单位成本就越低。这是:
A. Monte Carlo Analysis蒙特卡洛分析
B. Cause and Effect因果关系
C. Learning Curve Theory学习曲线理论
D. The Law of Diminishing Returns收益衰减法则
查看答案
A resource breakdown structure is a resource hierarchy. Which of the following is usually used to break it down?资源分解结构是一种资源层级结构,通常按以下哪个来分解?
A. Resource category and quantity资源类别和数量
B. Resource category and type资源类别和类型
C. Resource category and usage time 资源类别和使用时间
D. Resource categories and costs 资源类别和成本
Which of the following are GENERALLY illustrated BETTER by bar charts than network diagrams?总的说来,下面哪个选项在横道图中比网络图中能得到更好的图示?
A. Resource trade-off资源权衡
B. Critical paths关键路线
C. Logical relationships逻辑关系
D. Progress or status进展或状态
Unlike bar charts, milestone charts show____里程碑图与横道图不一样, 它显示了______
A. Scheduled start or completion of major deliverables and key events可交付成果和主要事件预定的开始和完成时间
B. Activity starts and end dates活动开始和结束日期
C. Expected durations预期的持续时间
Dependencies活动之间的依附性
PERT is: PERT是指?
A. The longest path最长路径
B. A weighted average technique加权平均技术
C. A simulation technique模拟技术
D. Widely used in practice to determine schedule durations在决定进度历时时广泛应用