进行工期优化时,优先选择下列( )缩短持续时间。

A. 缩短持续时间对质量影响不大的关键工作;
B. 缩短持续时间对安全影响不大的关键工作;
C. 有充足储备资源的关键工作;
D. 缩短持续时间所需增加的费用最少的工作。

查看答案
更多问题

当计算工期超过计划工期时,可压缩关键工作的持续时间以满足要求,在确定缩短关键工作的持续时间时,宜选择缩短持续时间所增加的费用相对较少的工作。

A. 对
B. 错