The project manager’s role during execution of the project can BEST be described as a (an):在项目执行阶段,对项目经理角色最确切的描述是:
A. Director.指导者
B. Integrator.整合者
Coordinator.协调员
D. Leader.领导
查看答案
The project sponsor decided to interrupt funding for your project. You should?项目发起人决定中断你的项目的资金,你应该?
A. The project sponsor decided to interrupt funding for your project. You should?马上停止工作,并释放所有资源
B. Stop work immediately and release all resources.缩小团队规模
C. Decrease team size开始项目收尾
D. Start closing the project.删除非关键任务
E. Remove non-critical tasks.
The requirement to complete the project in three months using only four resources is an example of:项目要求在三个月内完成,而只投入4个资源,这是一个什么情况的例子?
A. constraints.制约因素
B. earned value analysis components.实现值分析组成
C. benefit cost ratios.收益成本比率
D. law of diminishing returns.收益递减法则
Which of the following BEST describes formal acceptance of a project?下面哪项最好的描述了项目的正式接受?
A. Substantial completion is reache确实已经完成项目
B. Customer signoff of the product is documente客户签收项目产品的交付文档
C. Final payment is made.最终付款完成
D. Final deliverables are sent to the customer. 最终可交付使用成果送达客户
Which of the following best describes the purpose of project change control?以下哪个最好地描述了开展项目变更控制的目的?
A. Ensure that all changes are approved and that only approved changes can be included in the plan 确保所有变更都经过批准,确保只有经批准的变更才能纳入计划中
B. Ensure all changes are approved by the change control committee and incorporated into the plan after approval 确保所有变更都经过变更控制委员会的审批,并在批准后纳入计划中
C. Ensure that project changes are kept to a minimum 确保把项目变更控制在最少的范围内
D. Ensure that only the most important stakeholders can make a change request and participate in the approval of the change request确保只有最重要的干系人才能提出变更请求,并参与对变更请求的审批工作