Which of the following statements about critical path is false()
A. Critical path is the longest path in the project network
B. Critical path shows the shortest duration of the project
Critical path is unique
Determines the overall project duration
查看答案
The formats presentation of the project schedule includes()
A. Bar charts
B. Milestone charts
C. Project schedule network diagrams
D. The pie chart
Question 13 is based on the passage of question 11.In the writer’s opinion, what is the best way to learn grammar()
A. Playing games with a set of rules
B. Learning grammar naturally as you grow up
C. Recalling how you learned your mother tongue
Doing a lot of grammar exercises
The Discounted Cash Flow (DCF) techniques include()
A. Net Present Value
B. Payback period
C. Internal Rate of Return
D. Annual cash flow
Question 14 is based on the passage of question 11.What’s the difference between teachers’ opinions in the way of learning grammar()
A. More exercises vs. more activities. span>
B. More activities vs. less exercises span>
C. Less exercises vs. more grammar rules. n>
D. More exercises vs. less activities. > n>