When did Mr. Knight probably submit the form?
A. December 7
B. December 12
C. January 11
D. January 14
根据《标准施工合同文件》,关于施工进度与工期,下列说法中正确的有()。
A. 经监理人批准的施工进度计划称合同进度计划
B. 实际进度与合同进度计划发生偏离时,承包人可以向监理人提交修订合同进度计划的申请报告
C. 监理人在发出开工通知前应获得发包人同意
D. 发包人增加了合同工作内容,承包人不一定能获得延长工期的许可
E. 因承包人原因造成竣工延误,承包人支付了逾期违约金,可部分免除修补缺陷义务E.
根据《标准施工招标文件》,下列因不可抗力而发生的费用或损失中,应由发包人承担的有()。
A. 承包人的人员伤亡相关费用
B. 已运至施工场地的材料和工程设备的损害
C. 因工程损害造成的第三者财产损失
D. 承包人设备的损坏
E. 承包人应监理人要求在停工期间照管工程的人工费用E.
Which of the following is NOT true?
A. If the teacher well unites his students and creates a positive atmosphere, he then will complete his task.
B. If guidelines are not acceptable both to students and teachers, the classroom can be a mess.
C. Outside pressures may cause stress among students.
D. Students need the teacher just as sheep need a shepherd.