常规的变更请求包括哪些方面?

查看答案
更多问题

A change control system should be created:变更控制系统应该被创建:

As needed on the project.根据项目需要.
By management.由管理层
C. As a formal documented procedure.一套正式书面程序
D. By the team.由项目团队

All technical work is completed on the project. Which of the following remains to be done?项目所有的技术工作都已完成,下面哪项是接下来要做到的?

A. Project budget项目预算
B. Risk management plan风险管理计划
C. Staff management plan职员管理计划
D. Lessons learned经验教训总结

An oil field development project manager believes that modifying the project scope may increase production and will increase the owner’s profit level. What should the project manager do? 一个油田开发项目的经理认为修改项目范围可以增加产量并提高业主的利润率,他应该:

A. Change the WBS变更WBS
B. Contact the customer to improve understanding联系客户、加强了解
Call a meeting with the project team召集项目团队会议
D. Update the scope management plan更新项目管理计划

Project integration management knowledge area项目整合管理知识领域。

A. Higher than other nine knowledge areas高于其他九大知识领域
B. Relatively independent of the other nine areas of knowledge相对独立于其他九大知识领域
C. It is mainly used to integrate the sub projects to form a comprehensive project plan主要用于整合各分项计划,来形成综合性的项目计划
D. Coordinate and unify all processes in other nine knowledge areas协调与统一其他九大知识领域的所有过程