A project , SPI=1.05 ,CPI = 0.5,How about the status of the project?一个项目SPI=1.05 ,CPI = 0.5,目前的状态?
Ahead of schedule, underrun. 进度提前,成本超支
B. Underrun, behind of schedule。成本节约,进度滞后
C. Behind of schedule, orverrun 进度滞后,成本超支
D. Ahead of schedule, overrun进度提前,成本超支
In the preparation of project budget, the cost baseline of each period is usually determined to be slightly higher than the expected cost expenditure, so as to (). 在编制项目预算时,通常会把各时期的成本基准确定为略高于预计的成本支出数,以便()。
Allow appropriate progress ahead允许适当的进度提前
B. Dealing with the occurrence of known risks 应对已知风险的发生
Consider estimated debt考虑预计的债务
D. All of the above 以上都是