题目内容

An advantage of a firm fixed price contract for the buyer is:固定总价合同对于买方的一个优点是:

A. Cost risk is lower 成本风险小
B. Cost risk in higher 成本风险大
C. There is little risk 很小的风险
D. Risk is shared by all parties 风险被所有参与共担

查看答案
更多问题

In which type of contract, Contractor is most concerned in Cost Estimate?以下哪种合同让承包商最关心成本估算?

A. Firm Fixed 固定价
B. CPIF成本加激励费
C. Time & Material 工料合同
D. Cost plus fixed fee , CPF成本加固定费用合同

The end of purchase input includes 结束采购的输入包括()。

A. Procurement file 采购文件
B. Procurement documentation 采购文档
C. Proposal建议书
D. Contract合同

Tom’s project seemed to hit a snag when the contractor completed the required component, as defined in the Statement of Work. The contractor delivered on the promise date, as specified, but the buyer was not pleased with the results. Tom should consider the contract to be:汤姆的项目似乎遇到了麻烦:虽然承包方完成了如工作说明书确定要求的部分,按照规定如期交付,但是买方对此结果并不满意。Tom应该把合同考虑为:

A. Complete because the contractor was satisfied 完成了,因为承包方满意了
B. Complete because the contractor satisfied the terms and conditions of the contract 完成了,因为承包方满足了合同的条款和条件
C. Incomplete because the buyer did not feel the contractor fulfilled the terms of the contract 没有完成,因为买方并不认为承包方完成了合同要求的条款
D. Incomplete because the original specifications were not properly prepared 没有完成,因为没有适当地准备初始规格

You are working on your research and development project when your customer asks you to include a particular component in the project.You know this represents new work, and you do not have excess funds available. What should you do?你正在做你的研发项目,这时你的客户要求你在项目中增加一个特殊组分。你知道这意味着新的工作并且你也知道项目没有剩余款。你应该怎么做?

A. Delete another lower priority task to make more time and funds available.取消另一个优先等级低的任务,以便腾出更多的时间和资金
B. Use funds from the management reserve to cover the cost.使用管理储备的资金来支付新任务的成本
C. Follow the contract change control process.按合同变更控制过程办理
D. Ask for more funds from the project sponsor.向项目发起人要更多的资金

答案查题题库