()is the process of formalizing acceptance of the completed project deliverables
A. Define Scope
B. Validate Scope
Creat WBS
D. Control Scope
查看答案
()is the process of identifying and documenting relationships among the project activities
A. Define Activities
B. Sequence Activities
C. Estimate Activity Durations
Develop Schedule
In order to ensure the realization of the project schedule, a resource demand plan corresponding to the schedule plan should be prepared. If the resource conditions are not met,()should be adjusted
A. The schedule plan
B. The schedule goal
C. The cost plan
D. The resource plan
Documents can be used for data analysis in Collect Requirements include()
Agreements
B. Marketing literature
C. Business rules repositories
D. Current process flows
Approaches for creating WBS include()
A. Top-down or bottom-up approach
B. Organisation-specific guidelines
C. WBS templateS
D. Brainstorming