Documents can be used for data analysis in Collect Requirements include()
Agreements
B. Marketing literature
C. Business rules repositories
D. Current process flows
查看答案
Approaches for creating WBS include()
A. Top-down or bottom-up approach
B. Organisation-specific guidelines
C. WBS templateS
D. Brainstorming
Enterprise environmental factors that influence the Define Activities process include()
A. Organizational cultures and structure
B. Schedule management plan
C.Published commercial information from commercial databases
D. Project management information system (PMIS)
Question 15 is based on the passage of question 11.What is the main idea of the passage()
A. Memorizing rules is required for learning grammar
B. Doing a lot of exercises helps learn grammar
C. Playing games helps learn grammar better
D. There are different ways to learn grammar
Which of the following statements about critical path is false()
A. Critical path is the longest path in the project network
B. Critical path shows the shortest duration of the project
Critical path is unique
Determines the overall project duration