The accuracy of the deterministic estimate is确定性估算的准确度是()。
A. ±5%
B. ±10%
C. ±20%
D. ±50%
查看答案
What is the cost of team training团队培训是以下哪种成本?
A. Direct cost 直接成本
B. Net present value, NP净现值
C. Indirect costs 间接成本
D. Fixed costs 固定成本
Using the PMBOK definition of contingency reserve, which of the following statements about contingency reserves is false?按项目管理知识体系对应急储备的定义,以下哪个关于应急储备的陈述是错误的?
A contingency reserve is a separately planned quantity used to allow for future situations which may be planned for only in part. 应急储备是单独计划的资金用于未来那些可能只计划了一部分的情况。
B. Contingency reserves may be set aside for known unknowns. 应急储备为已知未知的境况而准备的资金。
Contingency reserves may be set aside for unknown unknowns. 应急储备为未知未知的境况而准备的资金。
D. Contingency reserves are normally included in the project's cost and schedule baselines. 应急储备通常包含在项目成本和进度的基线中。
The performance measurement baseline is the.绩效测量基准是
A. BAC
B. EV
C. AC
D. ACWS
You are a project manager for a small construction project.Your project was budgeted for US $72,000 over a six-week period.As of today, you've spent US $22,000 of your budget to complete work that you originally expected to cost US $24,000.According to your schedule, you should have spent US $30,000 by this point.Based on these circumstances, your project could be BEST described as: 你是一个小型建设项目的经理,项目预算为72,000美元,工期六个星期。到今天为止,你消耗了22000美元的预算,完成了最初计划需要24000美元的工作。根据进度,你应该花费30000美元。根据这些情况,你的项目状态为:
Ahead of schedule.进度提前
Behind schedule.进度滞后
C. On schedule. 符合进度计划
D. Having not enough information provide 没有足够的信息判断