题目内容

The following statements about resource leveling are all correct except以下关于资源平衡的说法都是正确的,除了()。

A. Distribute resources equally in each period of the project so as to make a stable schedule plan 在项目各时段中平均分配资源,以便制订出平稳的进度计划
B. Adjust the schedule according to resource constraints 根据资源制约因素,来调整进度计划
C. Solve the problem that the same resource is allocated to two jobs at the same time解决同一资源在同一时间被分配至两个工作的问题
D. Adjust the project schedule while keeping the critical path unchanged在保持关键路径不变的前提下,调整项目进度计划

查看答案
更多问题

Peter is a project manager. To control schedule, he is reanalyzing the project to predict the duration of the project, analyzing the sequencing of activities with minimal schedule flexibility. What method did he use?彼得是一位项目经理。为控制进度,他正对项目进行重新分析以预测项目历时,他分析了在最小的进度灵活性下的活动排序。请问他使用了什么方法?

A. Flow chart method, 流程图法
B. Critical path method 关键路径法
C. Precedence Diagramming Method, PD紧前关系绘图法
D. WBS, 工作分解结构

In order to reduce the influence of Parkinson's law, should?为了减少帕金森定律的影响,应该?

A. Increase the expected schedule of activities将活动的预期进度时间安排增加
B. Reduce the expected schedule of activities将活动的预期进度时间安排减少
C. Keep the expected schedule of activity unchanged将活动的预期进度时间安排不变
D. According to the actual situation 将进度按照实际情况

You are managing a construction project for a new city water system. The contract requires you to use special titanium piping equipment that is guaranteed not to corrode. It also requires the use of kryptonite bolts to assemble the piping system. Because kryptonite has a mass density that is 16 times its weight, the pipe must be resting in the ground a total of 10 days before the bolts can be installe In this example, the 10-day period is defined as你负责管理一个城市用水系统项目。为了避免水管生锈,合同上要求使用铁合金的管道设备, 此外还要用不锈钢铆钉来组装这些管道。根据某些技术要求,这些管道放置好以后要过10天才能装铆钉。这10天被称作:

A. Lag滞后时间
B. Lead前置时间
C. Float浮动时间
D. Slack松弛时间

Many schedule activities can be implemented with various schemes, such as using different tools, different human resources, different machines, etc. The analysis of various possible implementation methods belongs to: 很多进度活动都可以采用多种方案加以实施,如使用不同的工具、不同的人力资源、不同的机器等。对各种可能的实施方法进行分析属于()。

A. Made by self or outsourcing 自制或外购分析
B. Project reserve analysi项目储备分析
C. Benefit cost analysis效益成本分析
D. Alternatives Analysis 备选方案分析