题目内容

在工程网络计划中,工作M的最早开始时间为第17天,其持续时间为5天,该工有三项紧后工作,它们的最早开始时间分别为第25天、第27天和第30天,则工作M的自由时差为()天。

A. 13
B. 8
C. 5
D. 3

查看答案