Which of the following items should not be included in the software project management plan?

A. the techniques and case tools to be used andthe life cycle model to be used
B. detailed schedules, budgets and resource allocations
C. the organisational structure of the development organisation, project responsibilities, managerial objectives and priorities
D. all of these aspects should be included

查看答案
更多问题

If a specification statement is to be testable then it one of the properties it must have is:

A. tenacity
B. longevity
C. verifiability
D. traceability

A fault to look for during testing of the products design is:

A. logic fault and interface fault
B. lack of exception handling
C. non-conformance to specifications
D. all of theses are examples of faults to look for during testing of the products design.

Why is it necessary to carry out acceptance testing?

A. The test group may not be competent enough.
B. To receive the final payment for the completed product.
C. It is not until this stage of the testing that the system as a whole (hardware and software) is exercised.
D. The users may use a combination of functions and data that are not anticipated by the developers.

The final form of testing COTS software is () testing.

A. unit
B. integration
C. alpha
D. beta