某工程网络计划共有10项工作,其中A工作为起始工作,其紧后工作为B,B工作的紧后工作为C,持续时间分别为3天,4天,4天,B工作的总时差为2天,则B工作的最迟开始时间为()。

A. 3天
B. 4天
C. 5天
D. 7天