The resource calendar is the output of which of the following processes? 资源日历是以下哪个过程的输出?
A. Estimate resource requirements估算资源需求
B. Conduct procurements实施采购
C. Develop schedule plan 制订进度计划
Develop human resource plan制订人力资源计划
查看答案
A cost-plus-incentive-fee (CPIF) contract has an estimated cost of $150,000 with a predetermined fee of $15,000 and a share ratio of 80/20. The actual cost of the project is $130,000. How much profit does the seller make? 一份CPIF合同的估算成本为$150,000,预定费用为 $15,000,分享比例为 80/20。项目的实际成本为 $130,000。卖方获得了多少利润?
A. 31000
B. 19000
C. 15000
D. None of the above都不是
You need to use suppliers to provide several different products and services for your project. You want to create a document to describe the work in enough detail to allow prospective sellers to bid on them. What document should you create?你需要供应商为你的项目提供几种不同的产品和服务。你希望建立一个详细的文档,描述工作足够的细节以便供应商来竞标,这是什么文件?
A contract 合同
B. A proposal 建议书
C. A bidder's statement 投标人声明
D. A procurement SOW 采购工作说明书
Why is it more difficult to determine when change occurs on a project that is using a reimbursable type contract as compared to a lump-sum contract?与固定总价类合同项目相比,为什么很难确定成本补偿合同项目的变更发生时间?
A. The client usually creates change on a lump-sum type contract在固定总价合同项目中,客户通常发起项目变更
B. On reimbursable contracts, the client hope to change frequently对于成本补偿合同项目,客户希望频繁地发生变更
C. The detailed scope of work is not fully defined没有充分确定项目工作的详细范围
D. The contractor does not have right to refuse any change承包商没有拒绝变更的权力
The characteristic of cost reimbursable contract is 成本补偿合同的特点是()。
A. The buyer pays the seller the actual cost plus a management fee买方向卖方支付实际成本,外加一笔管理费用
B. The buyer pays the seller the actual cost plus a profit买方向卖方支付实际成本,外加一笔利润
C. The buyer pays the seller the actual cost plus a miscellaneous fee买方向卖方支付实际成本,外加一笔杂项费用
D. The buyer pays the seller the actual cost plus a bonus买方向卖方支付实际成本,外加一笔奖金