听力原文: The Shell oil company says villagers in the south-eastern part of the country have released the last of the more than 100 hostages they seized Saturday. The hostages are Nigerian employees of the Shell oil company. They were seized by the Ejaw ethnic group in Delta state. The hostages were seized to protest a decision by Nigeria's government to place a new municipal council in the territory of the opposing ethnic group. The dispute does not involve Shell oil company's policies.
Who held the hostages?

A. Workers of the Shell oil company.
B. Nigerian officials.
C. Villagers of an ethnic group in Nigeria.
D. Managing staff of the Shell oil company.

查看答案
更多问题

施工安全管理的工作目标要求按期开展安全检查活动,对查出的事故隐患的整改应达到整改“五定”要求,即:定整改责任人、定整改措施、定整改完成时间、定整改完成人和()

A. 定整改验收入
B. 定整改预算
C. 定整改方案
D. 定整改目标

建设工程项目结构主要部位的分部工程质量验收证明需要在各方验收后()内报工程质量监督机构备案。

A. 五天
B. 七天
C. 三天
D. 十五天

某土方开挖工程,某月计划完成土方量4 000m3,计划单价80元/m3,时至月底实际完成工程量为4 500m3,实际单价为78元/m3,通过赢得值法分析可知()。

A. 进度提前完成40 000元
B. 进度延误完成40 000元
C. 费用超支31 000元
D. 费用超支9 000元

通过该曲线,可以分析得到()。

A. 费用偏差为零
B. 费用偏差为负,费用超支
C. 进度偏差为零
D. 进度绩效指数为零