题目内容

Filtering is a concept that occurs when:过滤这个概念在什么时候出现?

A technique used in conjunction with a project communication plan一个技术结合项目沟通计划使用时
B. The supervisor performs verification and documentation of the results of a communications message监督人执行沟通信息审核和文档记载时
C. A large portion of the message was lost in upward or downward communications between a subordinate and supervisor 在上下级之间的沟通中大部分信息丢失
D. A and B,A和B

查看答案
更多问题

In the project team, communicate在项目团队中,沟通()。

A. The more, the better越多越好
B. Only for information that is conducive to the success of the project 只能针对那些有利于项目成功的信息
C. It should be done among all project team members应该在所有的项目团队成员之间进行
D. All information should be sent to all team members应该把所有信息发送给所有团队成员

Stakeholder may include: 项目干系人可能包括:

A. Customers or clients 客户
B. Citizen 市民
C. Supplier 供应商
D. All of above,以上全是

In order to effectively identify stakeholders, the following activities need to be carried out: (1) classify stakeholders; (2) identify stakeholders and their information; (3) develop stakeholder management plan; (4) evaluate the response of key stakeholders. The correct steps are:为了有效的识别干系人,需要进行以下活动:(1)对干系人进行分类;(2)识别干系人及其信息;(3)制定干系人管理计划;(4)评估关键干系人的反应。正确的步骤是:

A. (1)--(2)--(3)--(4)
B. (1)--(2)--(4)--(3)
C. (4)--(3)--(2)--(1)
D. (2)--(1)--(4)--(3)

All the following are true EXCEPT?下面哪项说法不正确?

A. the project manage rneedsto determine the skills of the stakeholders. 项目经理需要判断项目干系人的技能
B. the stakeholders’ impact on the project must be assesse项目干系人对项目的影响必须被评估
C. the stakeholders donot have a role in determining the project plan unless they are part of the project team . 在决定项目计划时不需要考虑项目干系人,除非他们是项目团队的一部分
D. Stakeholder management is part of the project plan.项目干系人管理是项目计划的一部分

答案查题题库