题目内容

A resource breakdown structure is a resource hierarchy. Which of the following is usually used to break it down?资源分解结构是一种资源层级结构,通常按以下哪个来分解?

A. Resource category and quantity资源类别和数量
B. Resource category and type资源类别和类型
C. Resource category and usage time 资源类别和使用时间
D. Resource categories and costs 资源类别和成本

查看答案
更多问题

Which of the following are GENERALLY illustrated BETTER by bar charts than network diagrams?总的说来,下面哪个选项在横道图中比网络图中能得到更好的图示?

A. Resource trade-off资源权衡
B. Critical paths关键路线
C. Logical relationships逻辑关系
D. Progress or status进展或状态

Unlike bar charts, milestone charts show____里程碑图与横道图不一样, 它显示了______

A. Scheduled start or completion of major deliverables and key events可交付成果和主要事件预定的开始和完成时间
B. Activity starts and end dates活动开始和结束日期
C. Expected durations预期的持续时间
Dependencies活动之间的依附性

PERT is: PERT是指?

A. The longest path最长路径
B. A weighted average technique加权平均技术
C. A simulation technique模拟技术
D. Widely used in practice to determine schedule durations在决定进度历时时广泛应用

During the duration compression you increased the resources to a critical path activity or activities. What must be further considered?在历时压缩过程中,你为关键路径活动增加了资源。接下去必须考虑什么呢?

A. The delay of the other activity其他活动的拖延
B. New critical activities come out产生新的关键活动
C. The resources assigned to the other tasks on the critical path分配到关键路径其他任务的资源
D. The longest task which resides in the schedule进度计划中工时最长的任务