某分部工程的网络计划如图7-1所示,计算工期为44天。A、D、I三项工作使用一台机械顺序施工。
[问题]
1.按A→D→I顺序组织施工,则网络计划变为图7-2。
(1)计算工期是多少天?
(2)机械在现场的使用和闲置时间各是多少天?
2.如按D→A→I顺序组织施工,则网络计划变为图7-3。
(1)计算工期是多少天?
(2)机械在现场的使用和闲置时间各是多少天?
3.试比较以上两个方案的优缺点。
4.监理工程师如批准按D→A→I顺序施工,施工中由于业主原因,B项工作时间被拖延5天,因此承包商提出要求延长5天工期。
网络计划如图7-4所示。
你认为工期延长几天合理?为什么?签发机械闲置(赔偿)时间几天合理?为什么?
A:the main feature/view of the Natural Approach
①Language is best taught when it is being used to transmit message.
②The Natural Approach claims to be able to incorporate any of the techniques of other methods.
③People acquire a language from what they hear and understand.
④Students' errors are not corrected unless meaning is affected.
⑤Class time is devoted primarily to providing input for acquisition.
B:the advantage or disadvantage associated with the feature
a. The techniques are often borrowed from other methods.
b. It emphasizes comprehensible and meaningful input.
c. It emphasizes the process of language acquisition rather than the product.
d. It stresses the importance of understanding.
e. Formal learning of language rules is of little value.
①