下列关于水利工程施工进度计划表达方法的说法正确的是:
A. 横道图不能反映各项工作之间的相互关系
B. 横道图能反映工程费用与工期之间的关系
C. 工程进度曲线能反映出实际工程进度
D. 工程进度曲线不能反映进度超前的时间
E. 工程进度曲线能反映后续工程进度预测
根据《水利工程建设项目招标投标管理规定》(水利部令第14号),水利工程建设项目施工招标应当具备的条件必须包括:
A. 初步设计已经批准
B. 建设资金来源已落实
C. 监理单位已确定
D. 施工图设计已完成
E. 有关建设项目征地和移民搬迁工作已有明确安排