投标人投标报价中关于暂列金额编制原则,说法正确的是()。
A. 按照其他项目清单中列出的金额填写,不得变动
B. 根据施工组织进行修改
C. 列入措施费
D. 列入管理费
查看答案
国外工程设计阶段的投资估算精度要求的误差控制在()以内。
A. ±5%
B. ±10%
C. ±15%
D. ±20%
根据题目要求完成下列任务。用中文作答。
教师教授了“过去进行时”这一语法内容,根据这一语法内容进行了如下练习活动。
Activity 1
T: Hi, what were you doing at $ p.m. yesterday?
S1: I was doing my homework.
T: Good. Ask the student behind you the same question.
S1: What were you doing at 8 p.m. yesterday?
$2: I was watching TV. What were you doing at 8 p.m. yesterday?
$3: I was cleaning my room. What were you doing at $ p.m. yesterday?
Activity 2
T: Now let‘s see who has the best memory. I was cooking at 6 o‘clock yesterday evening.What about you?
S1: I was having dinner.
T: Tell your partner like this: Ms. Zhang was cooking at 6 o‘clock yesterday evening. I washaving dinner.
S1: Ms. Zhang was cooking at 6 o‘clock yesterday evening. I was having dinner.
$2: Ms. Zhang was cooking at 6 o‘clock yesterday evening. S1 was having dinner. I wasdoing some shopping.
$3: ...
根据所设计的练习,回答下面三个问题。
(1)该教师设计的两个活动属于什么类型的语法操练活动?请简要说明。(6分)
(2)该设计中存在什么问题?(12分)
(3)针对存在的问题提出合理的建议。(12分)
工程项目的建设投资不包括内容为()。
A. 工程费用
B. 流动资金
C. 工程建设其他费用
D. 预备费
资格预审的项目概况与招标范围应说明()。
A. 招标条件
B. 招标文件的获取
C. 招标项目的建设地点
D. 招标项目的预计投资