题目内容
You recently created a complex resource plan named DB_PLAN that has two subplans named OLTP_PLAN and DSS_PLAN. The OLTP_PLAN and DSS_PLAN subplans are allotted 70 percent and 30 percent of the total CPU resources, respectively. The OLTP_PLAN subplan allocates 35 percent of the available CPU resources to a resource consumer group named ACCT_CLERKS. According to the OLTP_PLAN subplan, the remaining 65 percent of the available CPU resources is allocated to a second resource consumer group named MKT_CLERKS. The CPU resources available to the DSS_PLAN subplan are divided into two resource consumer groups named MKT_MANAGERS and FIN_MANAGERS. The MKT_MANAGERS group receives 65 percent of the available CPU resources, and the FIN_MANAGERS group receives 35 percent of the available CPU resources. What percentage of actual CPU resources will the resource consumer group, MKT_CLERKS, receive, if the DSS_PLAN subplan does NOT consume any CPU resources?()
查看答案
搜索结果不匹配?点我反馈