A project charter includes:项目章程包括:
A. Precedence diagramming methods前导图法
B. Task estimates任务估算
C. Detailed resource estimates详细的资源估算
D. High-level requirements项目的总体要求
A project is completed when: 项目在何时完工:
Administrative closure is achieved项目行政收尾已经完成
B. Deliverables have been accepted by the customer顾客已接受成果
C. All schedule dependencies have been integrated所有计划从属关系已经整合
D. Final project cost figures have been reconciled最后项目成本数字已经核对
Integration is done by:整合由__________来做。
A. Senior management高级管理层
B. Project team member项目队伍成员
C. Project management consultant项目管理顾问
D. Project manager项目经理