A boss called a project manager and asked for a new report. As the project manager analyzed the information needs,he did not think that the boss needed such information. What shall the project manager do?.老板打电话给项目经理索要一份新的报告。项目经理分析了他的信息需求以后,认为老板不需要这样的信息。项目经理应该怎么做?
A. Find the most effective way to provide the requested information. 找到最有效的方法,提交老板所需要的信息
B. Such a request may be rejected if the information value is low. 如果信息价值很低,这样的请求可以拒绝
C. Request additional resources and cost necessary for additional information. 申请额外的资源和成本,为老板编制额外的信息
D. Have a team meeting in order to understand the background of the boss’s request. 召开团队会议来了解老板所要求的信息背景
A project team has members in 4 different locations with varying information systems. The project manager works with the project team. To determine how project information will be distributed, these methods are detailed in which document?项目团队成员工作在具有不同信息系统的四个地方,项目经理与这些成员一起工作,要想确定如何发布项目信息,下列哪个文件中详细描述了信息发布方法?
A. Overall project plan 项目总体计划
B. Activity definition 活动定义
Communication management plan 沟通管理计划
D. Staffing management plan 员工管理计划
At the beginning of a project, there were 5 team members. Due to the expansion of workload, the number of team members increased to 8. How many communication channels have been added?某项目最初有5 个团队成员,由于工作量扩大,团队人数增加到 8 人。沟通渠道增加了多少条?
A. 9
B. 10
C. 18
D. 28
Issue logs are used to record and monitor the resolution of problems. Which of the following is most useful to ensure problem solving?问题日志用来记录和监督问题的解决情况。以下哪项对于确保问题解决最有用?
A. The issue as a separate activity is included in the project schedule planning.把问题作为一个单独的活动,列入项目进度计划中。
B. The solution of the problem is included in the project work breakdown structure as a work package.把问题的解决方案作为一个工作包,列入项目工作分解结构中。
C. The project manager is personally responsible for developing and implementing solutions to problems.项目经理亲自负责制定和执行问题的解决方案。
Designate the person responsible for the resolution of the problem and specify the resolution date.为问题的解决指定责任人,并规定解决日期。