In which type of matrix structure would a project manager most likely have a command of technology()

A. Strong matrix
Balanced matrix
C. Weak matrix
D. Cross-cultural matrix

查看答案
更多问题

The main objectives of project management are()

A. Profitability, cost, time
B. Time, cost, quality, and/or scope
Customer satisfaction, cost, time
D. Calendar dates, facilities available, funding

In which organization structure would the project manager is fully responsible for the project()

A. Functional
B. Projectized
C. Strong matrix
D. Weak matrix

The person responsible for balance the time, cost and quality objectives to achieve project success is()

A. The Human Resources Department
B. The line manager
C. The project manager
D. The executive sponsor

The knowledge areas in PMBOK include:()

A. Scope management
B. Risk management
Cost management
D. Information management

答案查题题库