在某工程网络计划中,已知M工作的自由时差为3天,如果在执行中M工作持续时间拖了2天,则此工作M( )

A. 总时差不变,自由时差减少了2天
B. 不会使总工期延长
C. 自由时差不变,总时差减少2天
D. 不影响其后续工作的正常进行