题目内容

In a walkthrough which is driven by documentation, the faults are often detected by:

A. a member of the team responsible for drawing up the specifications
B. the representative of the SQA group
C. the presenter
D. the representative of the client

查看答案
更多问题

The primary role of the walkthrough leader is to:

A. correct any faults with the documents that are under review
B. critique the documents that are under review
C. present the documents that are under review
D. elicit questions and facilitate discussion
E. judge the development team

The number of steps in an inspection is:

A. dependent on the scope of the product that is to be inspected
B. 3
C. 4
D. 5

The first step in an inspection is:

A. overview
B. preparation
C. inspection
D. re-work

The second step in an inspection is:

A. overview
B. preparation
C. inspection
D. re-work

答案查题题库