题目内容

Sticky Wicket (SW) manufactures cricket bats using high quality wood and skilled labour using mainly traditional manual techniques. The manufacturing department is a cost centre within the business and operates a standard costing system based on marginal costs.
At the beginning of April 2010 the production director attempted to reduce the cost of the bats by sourcing wood from a new supplier and de-skilling the process a little by using lower grade staff on parts of the production process. The standards were not adjusted to refl ect these changes.
The variance report for April 2010 is shown below (extract).
The production director pointed out in his April 2010 board report that the new grade of labour required signifi cant training in April and this meant that productive time was lower than usual. He accepted that the workers were a little slow at the moment but expected that an improvement would be seen in May 2010. He also mentioned that the new wood being used was proving diffi cult to cut cleanly resulting in increased waste levels.
Sales for April 2010 were down 10% on budget and returns of faulty bats were up 20% on the previous month. The sales director resigned after the board meeting stating that SW had always produced quality products but the new strategy was bound to upset customers and damage the brand of the business.
Required
(a) Assess the performance of the production director using all the information above taking into account both the decision to use a new supplier and the decision to de-skill the process. (7 marks)
In May 2010 the budgeted sales were 19,000 bats and the standard cost card is as follows:
In May 2010 the following results were achieved:
40,000kg of wood were bought at a cost of $196,000, this produced 19,200 cricket bats. No inventory of raw materials is held. The labour was paid for 62,000 hours and the total cost was $694,000. Labour worked for 61,500 hours.
The sales price was reduced to protect the sales levels. However, only 18,000 cricket bats were sold at an average price of $65.
Required:
(b) Calculate the materials, labour and sales variances for May 2010 in as much detail as the information allows. You are not required to comment on the performance of the business. (13 marks)

查看答案
更多问题

对违反行政纪律情节较重,造成较大损失或者不良后果的,给予________或________处分。

背景资料
某抛石斜坡结构防波堤工程总长800m,采用常规的爆炸排淤填石法处理水下软土地基,护面块体采用12t扭王字块,堤顶设置混凝土挡浪墙。工程施工中,堤心石爆填施工的一次推进距离为12m。爆填施工完成后,按体积平衡法推算出置换淤泥的范围与深度满足设计要求。扭王字块采用自上而下规则安放,块体在坡面上竖向摆放,块体间互相靠紧。 对挡浪墙混凝土的配合比进行了优化,掺人优质粉煤灰取代15%的水泥,采用超量取代,k=1.3,优化后混凝土的胶凝材料用量为376.2kg/m3。 该工程招标文件工程量清单中堤心石工程量为80万m3。合同规定:堤心石综合单价为65元/m3,当实际工程量超过清单工程量,且超过的数量大于10%时,综合单价调整为60元/m3。工程实际完成并经监理签认的堤心石工程量为100万m。。
问题
1.简述爆炸排淤填石法形成堤身的过程。
2.根据背景材料,指出本工程施工中存在的问题,说明理由。
3.优化后的挡浪墙混凝土配合比中的水泥用量是多少? 4.实际完成的堤心石工程款是多少万元?

背景资料
某重力式码头主体工程施工分3个流水段进行,段问、段内施工工艺互无干扰。抛石基床(包括挖泥、抛石、夯实、整平)、沉箱安放(包括预制、出运、安装、箱内填料)、上部结构(包括沉箱封顶混凝土、胸墙及面层混凝土浇筑)分项工程各只有一个专业施工队施工。各分项工程所需工时如下表所列:
【问题】
1.根据表列项目与工时绘制施工进度计划横道图和双代号网络图(按每项工作最早开始时间安排)。
2.判断整个施工过程中有几条关键线路?用结点和箭头连接的方式指出关键线路(例如①→②→③…)。
3.C1工作因故耽误了3周,是否影响总工期?为什么?这时的总工期是多少?
4.B1工作因故耽误了3周,是否影响总工期?为什么?这时的总工期是多少?

按照卫生部规定的计划免疫程序中不应包括的疫苗是()

A. 脊髓灰质炎疫苗
B. 甲型肝炎疫苗
C. 乙型肝炎疫苗
D. 麻疹疫苗
E. 白、百、破类毒素混合制剂

答案查题题库