题目内容

Project management processes can be categorized into five groups . the process groups are linked by the results they produce. the output s of one of ten become the input to another. What is the most appropriate sequence of the five project management process groups ?项目管理过程可以划分成5组。这5个过程通过它们产生的结构衔接起来,一个过程组的成果变成了另一个过程组的依据。这5个管理过程组最恰当的排序是什么?

A. Initiating‐planning‐monitoring and controlling‐executing‐closing启动-规划-监控-执行-收尾
B. Initiating‐executing‐monitoring and controlling‐planning‐closing启动-执行-监控-规划-收尾
C. Initiating‐planning‐executing‐monitoring and controlling‐closing启动-规划-执行-监控-收尾
D. Initiating‐monitoring and controlling‐planning‐executing‐closing启动-监控-规划-执行-收尾

查看答案
更多问题

The lessons learned from the project are meaningful because it:从项目中学到的经验教训是有意义的,因为它:

A. Show the cause of the deviation and the reason for choosing some corrective measures显示偏差的原因以及选择一些纠正措施的理由
B. Must be aggregated to meet organizational policies and procedures必须汇总起来以满足组织策略和程序的要求
C. Show why organizations choose certain items显示组织机构为什么选择某些项目
D. Show why some people are selected as project managers and team members显示为什么有些人被选为项目经理和团队成员

There are two projects: A project has 18 months, NPV=350; Bproject has 24 months, NPV=400. Which project would you choose? 有两个项目:A项目,18个月,NPV=350;B项目,24个月,NPV=400。你会选择那一个项目?

A. Choose A, because NPV is small 选A,因为NPV小
B. Choose A, because it takes a short time 选A,因为历时短
Choose B, because it takes a short time 选B,因为历时长
D. Choose B, because NPV is large 选B,因为NPV大

Which of the following is true about the monitoring process?以下关于监控过程的说法,哪个是正确的?

A. Monitoring is usually carried out by special personnel监控工作通常要由专人来开展
B. We should not only monitor the work of each stage, but also monitor the coordination between each stage不仅要监控各阶段的工作,而且要监控各阶段之间的协调
C. Monitoring only needs to be carried out for the execution process group监控只需要针对执行过程组进行
D. Some small changes may not need to be submitted to the overall change control process for comprehensive review 有些很小的变更可能不需要提交给整体变更控制过程做综合评审

Which of the following processes does not belong to the monitoring and controlling process group?以下哪个过程不属于监控过程组?

A. Verify Scope核实范围
B. Reporting performance报告绩效
C. Management procurement管理采购
D. Manage project team管理项目团队