●A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager's company, but the customer wants to pursue a solution at the meeting.The project manager should (72) .
(72)

A. tell the customer that he will not address any problems becausethis is only an information exchange meeting
B. tell the customer that the problem is not sufficiently defined to determine the appropriate action
C. collect as much information on the problem without committing his company to a solution
D. give the customer a range of solutions that might be acceptable to his Company

查看答案
更多问题

●最能反映小型企业内大多数职工工资状况的统计指标是全体职工工资的 (14) 。
(14)

A. 平均值
B. 中位数
C. 频数
D. 方差

●CORBA是由OMG组织为解决分布式处理环境中软硬件系统互连而提出的一种解决方案,已经逐渐成为分布计算技术的标准。CORBA标准主要分为三个层次,其中规定业务对象有效协作所需的协议规则的层次是(29)。
(29)

A. 对象请求代理
B. 公共对象服务
C. 公共语言规范
D. 公共设施

●某大型系统集成项目由多个不同的承包商协作完成,项目涉及了分别代表7家公司的24个主要干系人。项目经理陈某直接管理的团队有7个项目小组长,每个项目小组长负责一支约15人的工作组。陈某意识到必须特别注意进行有效的整体变更控制,这表明他最应该关心的工作是(56)。
(56)

A. 整合从项目的不同专业职能部门交付来的工作成果
B. 设立一个专门的变更控制部门来监控所有的项目变更
C. 保持基准计划的完整性,整合产品和项目的范围,并且协调那些跨知识领域的变更
D. 关注可能引发变更的因素,确定已发生的变更并管理实际发生的变更