Two common methods of drawing progress network are两种常用的进度网络绘图方法是()。
Aticivity on node method(AON) and Atitivity on arrow method (AOA) 节点法与箭线法
B. Aticivity on node method(AON) and Conditional diagramming methods 节点法与条件图法
C. Aticivity on node method(AON) and Logical bar chart method节点法与逻辑横道图法
D. Aticivity on node method(AON) and Precedence Diagramming Method (PDM) 节点法与前导图法
查看答案
A project manager is assigned to a project that he has never done before. The project manager has made a schedule for the project, and will improve the successor schedule at the end of the current stage. Which of the following best describes he is doing? 一个项目经理被分配到一个项目,他以前从来没有做过这类似的项目。项目经理为项目制定了进度计划,并在当前阶段工作即将结束时完善随后项目阶段的进度计划。下列哪项最恰当地描述了 项目经理正在做的事?
A. Control process to ensure corrective actions are taken when necessary to achieve project objectives确保在必要时采取纠正措施以达到项目目标的控制过程
B. Compilation process of change control plan变更控制计划的编制过程
C. Progressive process of rolling planning滚动式规划的递进过程
D. Repeat the core planning process from one project to another in the same order从一个项目到另一个项目以相同的顺序重复计划的核心计划编制过程
The final result of defining the activity process is 定义活动过程所得到的最终成果是()。
A. Deliverables 可交付成果
B. Activities 活动
C. Workpackage 工作包
D. Work tasks 工作任务
"I cannot test the software until I code the software." This expression describes which of the following dependencies?"在编码完成之前,我不可能测试软件。"这种观点代表了下列哪种依赖关系?
A. Discretionary灵活性的依赖关系
B. Soft软逻辑关系
C. Preferential优先逻辑
D. Mandatory or hard强制性依赖关系或硬逻辑关系
The following statements about resource leveling are all correct except以下关于资源平衡的说法都是正确的,除了()。
A. Distribute resources equally in each period of the project so as to make a stable schedule plan 在项目各时段中平均分配资源,以便制订出平稳的进度计划
B. Adjust the schedule according to resource constraints 根据资源制约因素,来调整进度计划
C. Solve the problem that the same resource is allocated to two jobs at the same time解决同一资源在同一时间被分配至两个工作的问题
D. Adjust the project schedule while keeping the critical path unchanged在保持关键路径不变的前提下,调整项目进度计划