Your project is approximately 70% complete and progressed according to plan . There are nine teams working on implementation and testing activities . You receive notification that two teams are falling behind relative to the other . The MOST likely reason

A. the scope of work has changed .
B. a weak matrix project organization .
C. unidentified risks .
D. low morale due to compensation issues .