题目内容

A network diagram that uses nodes to represent activities and arrows to show the activity dependencies and allows no loops is called: 用节点代表活动,箭线表示活动依赖关系,并且不允许回路的网络图被称为:

AOA(双代号网络图)
B.AON(单代号网络图)
C.ADM(箭线图)
D. GERT(图形评审技术)

查看答案
更多问题

Two common methods of drawing progress network are两种常用的进度网络绘图方法是()。

Aticivity on node method(AON) and Atitivity on arrow method (AOA) 节点法与箭线法
B. Aticivity on node method(AON) and Conditional diagramming methods 节点法与条件图法
C. Aticivity on node method(AON) and Logical bar chart method节点法与逻辑横道图法
D. Aticivity on node method(AON) and Precedence Diagramming Method (PDM) 节点法与前导图法

A project manager is assigned to a project that he has never done before. The project manager has made a schedule for the project, and will improve the successor schedule at the end of the current stage. Which of the following best describes he is doing? 一个项目经理被分配到一个项目,他以前从来没有做过这类似的项目。项目经理为项目制定了进度计划,并在当前阶段工作即将结束时完善随后项目阶段的进度计划。下列哪项最恰当地描述了 项目经理正在做的事?

A. Control process to ensure corrective actions are taken when necessary to achieve project objectives确保在必要时采取纠正措施以达到项目目标的控制过程
B. Compilation process of change control plan变更控制计划的编制过程
C. Progressive process of rolling planning滚动式规划的递进过程
D. Repeat the core planning process from one project to another in the same order从一个项目到另一个项目以相同的顺序重复计划的核心计划编制过程

The final result of defining the activity process is 定义活动过程所得到的最终成果是()。

A. Deliverables 可交付成果
B. Activities 活动
C. Workpackage 工作包
D. Work tasks 工作任务

"I cannot test the software until I code the software." This expression describes which of the following dependencies?"在编码完成之前,我不可能测试软件。"这种观点代表了下列哪种依赖关系?

A. Discretionary灵活性的依赖关系
B. Soft软逻辑关系
C. Preferential优先逻辑
D. Mandatory or hard强制性依赖关系或硬逻辑关系