题目内容

In which of the following project phases is the project cost budget prepared?项目成本预算在下列哪一个项目阶段编制?

A. Initiating启动阶段
Before the project lifecycle begins 在项目生命周期开始之前
C. Planning规划阶段
D. Executing执行阶段

查看答案
更多问题

Planning process groups are generated:规划过程组会产生。

A. Project management plan 项目管理计划
B. stakeholder register and stakeholder management strategy 干系人登记册和干系人管理策略
C. project manager plan and project documents项目经理计划和项目文件
D. project management plan and procurement documents项目管理计划和采购文件

Project management process group.项目管理过程组。

A. Overlap with each other to varying degrees throughout the project在整个项目期间都以不同程度相互重叠
B. The five process groups will work in different order on different projects五大过程组在不同的项目上会以不同的顺序进行
C. Is independent of each other, and each process group only executes once on each project是相互独立的,而且每个过程组在每个项目上只执行一次
D. Equivalent to project phase等同于项目阶段

Project management processes can be categorized into five groups . the process groups are linked by the results they produce. the output s of one of ten become the input to another. What is the most appropriate sequence of the five project management process groups ?项目管理过程可以划分成5组。这5个过程通过它们产生的结构衔接起来,一个过程组的成果变成了另一个过程组的依据。这5个管理过程组最恰当的排序是什么?

A. Initiating‐planning‐monitoring and controlling‐executing‐closing启动-规划-监控-执行-收尾
B. Initiating‐executing‐monitoring and controlling‐planning‐closing启动-执行-监控-规划-收尾
C. Initiating‐planning‐executing‐monitoring and controlling‐closing启动-规划-执行-监控-收尾
D. Initiating‐monitoring and controlling‐planning‐executing‐closing启动-监控-规划-执行-收尾

The lessons learned from the project are meaningful because it:从项目中学到的经验教训是有意义的,因为它:

A. Show the cause of the deviation and the reason for choosing some corrective measures显示偏差的原因以及选择一些纠正措施的理由
B. Must be aggregated to meet organizational policies and procedures必须汇总起来以满足组织策略和程序的要求
C. Show why organizations choose certain items显示组织机构为什么选择某些项目
D. Show why some people are selected as project managers and team members显示为什么有些人被选为项目经理和团队成员

答案查题题库