题目内容

什么是范围基准,是在什么时间确定的,范围基准包含的内容有哪些?

查看答案
更多问题

Which of the following could be an appropriate WBS code for a work package at the fourth level in a WBS where the top level code is 1.0? WBS最高一级的编码为1.0,以下哪个可能是第四级的WBS工作包的编码?

A. 1.4
B. 1.1.1.1
C. 1.2.3.4
D. b and c

A project manager may use _______ to make sure the team clearly knows what work is included in each of their tasks?项目经理可以使用_______来保证项目团队清楚的了解到他们的每一项任务包含的工作。

A project scope of work项目工作范围
B. A project charter项目章程
C. A WBS dictionary WBS词汇表
D. A risk management plan风险管理计划

When a team member defines activities for a work package, find out that you say the current information is insufficient and cannot be broken down into specific activities. You instruct the member to break down the work package to the milestone level. What does this show?当一名团队成员为工作包定义活动时,找到你说目前信息不足,不能分解成具体的活动。你指示该成员,把工作包分解到里程碑的水平。这体现了?

A. 50-50Rules 50-50规则
B. 100% rule 100%规则
C. Rolling wave rule滚动式规划
D. You care about team members 你关心团队成员

A client has asked you to add scope of work to the project. The project is under budget and a little ahead of schedule. What should you do?客户要求你增加项目的工作范围,此项目在预算之内进度稍微提前。你应该做什么?

Approve the change批准这个变更
B. Let the client know the effects of the change on the project让客户知道变更对项目的影响
C. Ask approval from the sponsor for making the change请求项目投资人批准此变更
D. Get approval from the configuration change board从配置管理委员会获得批准