题目内容

Before starting a project, you should complete the following items, except.在开始一个项目之前,应该完成下列各项,除了。

Appoint project manager and set up project management team指定项目经理,并组建项目管理团队
B. Determine the overall needs of the project确定项目的总体需求
Carry out project feasibility study and evaluate alternatives进行项目可行性研究,评价备选方案
Determine the project objectives and explain the reasons for the project确定项目目标,并说明做项目的理由

查看答案
更多问题

In the PMBOK five project management process groups, which one has the highest level of activity throughout the life of project ? PMBOK描述的五大管理过程中,通常哪一过程将消耗最大资源?

A. Executing执行
B. Planning 计划
Controlling 控制
D. Initiating 启动

In which of the following project phases is the project cost budget prepared?项目成本预算在下列哪一个项目阶段编制?

A. Initiating启动阶段
Before the project lifecycle begins 在项目生命周期开始之前
C. Planning规划阶段
D. Executing执行阶段

Planning process groups are generated:规划过程组会产生。

A. Project management plan 项目管理计划
B. stakeholder register and stakeholder management strategy 干系人登记册和干系人管理策略
C. project manager plan and project documents项目经理计划和项目文件
D. project management plan and procurement documents项目管理计划和采购文件

Project management process group.项目管理过程组。

A. Overlap with each other to varying degrees throughout the project在整个项目期间都以不同程度相互重叠
B. The five process groups will work in different order on different projects五大过程组在不同的项目上会以不同的顺序进行
C. Is independent of each other, and each process group only executes once on each project是相互独立的,而且每个过程组在每个项目上只执行一次
D. Equivalent to project phase等同于项目阶段