The project charter should be approved by?项目章程由谁批准?
A. Project manager项目经理
B. Sponsors 项目发起人或投资人
C. Senior Project manager高级项目经理
D. Project team 项目团队
查看答案
The project manager receives a change request from the client, which does not affect the project time and is easy to complete. What should the project manager do first?项目经理从客户那里收到了一个变更请求,这个变更并不影响项目时间而且易于完成。这时候项目经理首先应该做什么?
A. Implement changes as soon as possible尽快执行变更
B. Contact project sponsor for permission与项目发起人联系获取许可
C. To change control committee去变更控制委员会
D. Overall impact of evaluation on other aspects of the project评价对项目其他方面的总体影响
What is the function of CCB?变更控制委员会(CCB)是什么职能的组织?
A. It is composed of representatives of main stakeholders who are responsible for approving or rejecting the change of project benchmark 由负责批准或否决项目基准变更的主要干系人的代表所组成
B. Consists of key project team members who are responsible for approving or rejecting project baseline changes由负责批准或否决项目基准变更的主要项目团队成员所组成
C. It is composed of the main administrative personnel responsible for approving or rejecting the change of project benchmark由负责批准或否决项目基准变更的主要行政人员所组成
D. It is composed of senior managers who are responsible for approving or rejecting the project benchmark change由负责批准或否决项目基准变更的高级管理人员所组成
Where are lessons learned documents used?经验教训文件用于哪里?
A. Executing 执行阶段
B. Initiating 启动阶段
C. Project life cycle 项目生命周期
D. Planning 规划阶段
A change control board is:变更控制委员会是:
A formally constituted group of stakeholders responsible for ensuring that only a minimal amount of changes occur on the project.正式组成的利害关系者小组负责保证项目的变量最小化
B. An informal or formal group of team members responsible for change to a project. 正式或非正式团队负责项目变更事宜
C. An informal group that has oversight of project implementation.非正式的小组对项目执行进行的监督
D. A formally constituted group of stakeholders responsible for approving or rejecting changes to the project baselines.正式组成的利害关系者小组负责审批或否决对项目基准计划的变更