All of the following are inputs to scope verification EXCEPT?

A. Work breakdown structure
B. Project Plan。
C. Work results
D. Change requests

查看答案
更多问题

Your project is approximately 70% complete and progressed according to plan . There are nine teams working on implementation and testing activities . You receive notification that two teams are falling behind relative to the other . The MOST likely reason

A. the scope of work has changed .
B. a weak matrix project organization .
C. unidentified risks .
D. low morale due to compensation issues .

如果银行能够对不同风险的项目要求不同的担保率,那么我们模型中的信贷市场配给有可能会消失。()

What is the decomposition process used to develop?

A. Management plan。
B. Communication plan。
C. Work breakdown structure。
D. Earned value。

在可行的激励指标中,基于产出的激励模式不能与公司长远发展目标相冲突。()

答案查题题库