Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:管理层已决定“赶工”一个项目,以避免因延迟交付而支付罚款。若要赶工该项目,应将加班或额外资源分配给:
All activities.所有活动
B. Only those activities with the longest time durations.仅仅历时最长的活动
C. Those activities on the critical path begining with the longest time duration activities.关键路径上的活动
D. Those activities with the greatest degree of risk.最大风险的活动
查看答案
Which of the following scheduling techniques incorporates a form of risk assessment?以下进度计划制订技巧中何种包含某种形式的风险评估?
Analogous estimating类比估算
B. Program Evaluation and Review Technique (PERT)/three point estimate 计划评审查技术/三点估算
C. Precedence Diagramming Method (PDM) 单代号图方法(PDM)
D. Critical Path Method (CPM)关键路线法(CPM)
A network diagram that uses nodes to represent activities and arrows to show the activity dependencies and allows no loops is called: 用节点代表活动,箭线表示活动依赖关系,并且不允许回路的网络图被称为:
AOA(双代号网络图)
B.AON(单代号网络图)
C.ADM(箭线图)
D. GERT(图形评审技术)
Two common methods of drawing progress network are两种常用的进度网络绘图方法是()。
Aticivity on node method(AON) and Atitivity on arrow method (AOA) 节点法与箭线法
B. Aticivity on node method(AON) and Conditional diagramming methods 节点法与条件图法
C. Aticivity on node method(AON) and Logical bar chart method节点法与逻辑横道图法
D. Aticivity on node method(AON) and Precedence Diagramming Method (PDM) 节点法与前导图法
A project manager is assigned to a project that he has never done before. The project manager has made a schedule for the project, and will improve the successor schedule at the end of the current stage. Which of the following best describes he is doing? 一个项目经理被分配到一个项目,他以前从来没有做过这类似的项目。项目经理为项目制定了进度计划,并在当前阶段工作即将结束时完善随后项目阶段的进度计划。下列哪项最恰当地描述了 项目经理正在做的事?
A. Control process to ensure corrective actions are taken when necessary to achieve project objectives确保在必要时采取纠正措施以达到项目目标的控制过程
B. Compilation process of change control plan变更控制计划的编制过程
C. Progressive process of rolling planning滚动式规划的递进过程
D. Repeat the core planning process from one project to another in the same order从一个项目到另一个项目以相同的顺序重复计划的核心计划编制过程