You prepared an integrated project plan and a project schedule. You submitted it to the steering committee, and it was approved. Key stakeholders accepted the plan. It is time to distribute it. Both the project plan and schedule should be distributed to你在准备一个综合项目计划和一个项目时间表。 你将它们提交给筹划指导委员会, 并得到了批准。 有关各方也接受了计划。 现在是分发这些计划的时候了。 项目计划和时间表应该分发给:
All stakeholders in the performing organization 组织中执行项目的所有有关各方
B. All project stakeholders 项目所有的干系人
C. Project team members and the' project sponsor 项目小组成员和项目发起人
D. People noted in the communications management plan 在沟通管理计划中指明的人
查看答案
The MOST likely result of communication blockers is that:沟通出现障碍时最可能的结果是:
A. The project is delayed. 项目被延迟
B. Trust level is enhanced. 增强了信任
Conflict occurs. 出现冲突
D. Senior management is displease 高级管理层很生气
Project Manager should --项目经理应该:
A. Control all the information.控制所有信息
B. Try to control communication 尽力控制沟通
C. Delegate control of communication委托控制沟通
D. Have enough information on the conflicts through communication system通过沟通系统获得足够的关于冲突的信息
Procurement audit is 采购审计()。
A. Identify deficiencies in Seller's workflow or deliverables识别卖方工作流程或可交付成果中的不足之处
B. Identify whether the project activities conform to the relevant policies, methods and processes of the organization and the project识别项目活动是否符合组织和项目的相关方针、方法及流程
Check the effectiveness of risk response measures in dealing with identified risks and their root causes检查风险应对措施在处理已识别风险及其根源方面的有效性
D. Structured review of all procurement processes from planning procurement to managing procurement对从规划采购到管理采购的所有采购过程进行结构化审查
The resource calendar is the output of which of the following processes? 资源日历是以下哪个过程的输出?
A. Estimate resource requirements估算资源需求
B. Conduct procurements实施采购
C. Develop schedule plan 制订进度计划
Develop human resource plan制订人力资源计划