题目内容

进行基础教育课程改革,要用探究式学习取代接受式学习。

查看答案
更多问题

该工程的实际工期为多少天?可得到的工期补偿和费用补偿各为多少天?

在现实中,身居管理者位置的人并不一定会自然具备正确给下属委派工作的能力。他们虽然也分配工作,但对工作的情况、下属的情况却不完全了解。常常把工作分配给不适当的人去做,结果当然很糟。你若作为某一单位或部门的管理者,该如何正确地给下属委派工作呢?

?Read this part of a fax from Sally Saunders, a hotel conference manager.
To: ______
Fax No: ______
From: Sally Saunders
Date: 1 March 2002
Pages (incl cover): 3
Thank you very much for your letter, enquiring about availability of conference facilities at this hotel for 1-4 September. I note your request for a special menu for the conference dinner on your final evening. You will find suggestions enclosed.
Unfortunately, during the week you have chosen for your conference, there is a trade fair. Therefore, we have very few single rooms available. I could offer you twin-bedded rooms, or perhaps you would consider moving your conference to the following week? I look forward to receiving your booking and choice of dishes for the conference dinner.
?Write a fax to Mrs Saunders:
?thanking her for her fax
?confirming your original dates for the conference
?booking 20 twin-bedded rooms
?telling her which dishes from the menu you require for the conference dinner,
?Write 60-60 words on your Answer Sheet.
?Do not include postal addresses.

基坑开挖进行18天时,发现-6m地基仍为软土地基,与地质报告不符。监理工程师及时进行了如下工作。
(1) 通知施工单位配合勘察单位利用2天时间查明地基情况。
(2) 通知业主与设计单位洽商修改基础设计,设计时间为5天交图。确定局部基础深度加深到-7.5m,混凝土工程量增加70m3。
(3) 通知施工单位修改土方施工方案,加深开挖,增大放坡,开挖土方需要4天。
【问题】
(1) 监理工程师应核准哪些项目的工期顺延?应同意延期几天?
(2) 对哪些项目(列出项目名称内容)应核准经济补偿?

答案查题题库